Vale’s performance in Q1 was marked by higher y/y iron ore sales and progress in the commissioning of the VGR1 and Capanema projects, ensuring greater operational flexibility and adherence to the 2025 production guidance. Copper and Nickel operational performance was strong, reflecting the consistent performance across all assets, as well as the ramp-up of the VBME project in Canada.

Iron ore production totaled 67.7 Mt, 4% (3.2 Mt) lower y/y, as per Vale’s mine plan, while high rainfall levels further impacted the Northern System. S11D continued to perform well, reaching the highest production ever for a first quarter. Pellets production totaled 7.2 Mt, 15% (1.3 Mt) lower y/y, due to lower pellet feed availability. Iron ore sales totaled 66.1 Mt, 4% (2.3 Mt) higher y/y, driven by Vale’s supply chain flexibility using advanced inventories.

Copper production totaled 90.9 kt, 11% (9.0 kt) higher y/y, with a strong operational performance at Salobo, Sossego and Voisey’s Bay following the ramp-up of Salobo 3 and Voisey’s Bay’s underground mines.

Nickel production totaled 43.9 kt, 11% (4.4 kt) higher y/y, mainly reflecting higher production at Onça Puma after the furnace rebuild in 1Q24 and stronger asset performance in Canada, further fueled by VBME’s ramp-up.

Click here for full report

 

Media Relations Office - Vale
imprensa@vale.com

Inhalte mit Press topics Investors .

Lupa de pesquisa

Did not find what you were looking for? Access our Search Center 

Reparation

Our commitment to repairing the communities and people impacted by the B1 dam failure is constant. See the social, environmental and safety actions taken by Vale. 
Imagem placeholder Imagem placeholder Foto:
Onda