Tutup

Karyawan Vale tersenyum di lanskap hijau. Dia mengenakan seragam Vale
hijau, kacamata, helm, dan penutup telinga. Artefak gelombang visual Vale
Imagem de header interno Imagem de header interno
com.liferay.portal.kernel.util.DateUtil_IW@2755f6b9
Photo: James Hodgins
com.liferay.portal.kernel.util.DateUtil_IW@2755f6b9
Photo: James Hodgins

As part of our commitment to environmental stewardship, Vale Base Metals (VBM) is moving forward with the dismantling of the copperstack and superstack at the Copper Cliff Smelter Complex. 

These structures have been decommissioned following the successful completion of the approximately $1 billion Clean Atmospheric Emissions Reduction (Clean AER) Project, which was a cornerstone initiative in our ongoing, long-term environmental stewardship program for Sudbury.

The Clean AER Project has enabled VBM’s Sudbury Operations to eliminate 100,000 metric tonnes of sulfur dioxide emissions each year (equivalent to 1,000 railway tanker cars of sulphuric acid), bringing emissions down to 30% below the provincial standard. 

How will the Copperstack come down?

The flue which fed the copperstack with emissions was removed in March of 2024. That means all that remains is the concrete structure. 

The entire base area of the copperstack is fenced off to protect the work site and surrounding operations of the Copper Cliff Smelter. Production at the smelter will not stop during this project.
Imagem placeholder Imagem placeholder Photo: Robert Alemany
Onda
video

A mast climber is affixed along the sides of the 450-foot structure. This rail mast climber operates like an elevator and will travel along the circumference of the stack.  At the top of the mast climber is the summit zone and work platform.  

The dismantling process will require six people using concrete crunchers and breakers and two demolition robotic excavators. The concrete exterior will be cut in 4-foot sections and debris will be discarded down the interior of the stack. Water misting will occur to suppress dust as this work occurs. The average size of the debris falling down the inside of the stack is the size of a basketball. 

As each piece of concrete gets cut away, the work platform is disassembled and gradually the mast climber’s overall height gets reduced as the project progresses. 

Dismantling activities will pause every five to ten days so debris from the base of the interior of the stack can be removed. During this period, no people are permitted to be at the summit zone working on platforms high above. 

The concrete shell will be removed from the smelter area and placed in a designated area within Vale’s Central Tailings Facility. This location is designed to for this purpose and will ensure that the rubble is safely contained, monitored and that all contact water is treated. 

Watch the video below to see how this process will work

How will the superstack come down? 

Since 2020 the superstack has been inactive but work on preparing it for dismantling has not stopped. Careful study and design work was needed to ensure the dismantling was safe for the community and our employees working in the smelter complex. Time was spent slowly cleaning the stack's interior, removing the steel liner and sealing or removing accessory structures in preparation for a future dismantling of the shell.  

We are currently evaluating the approach to its dismantling, and we will keep the community informed as our plans develop. 

When will the superstack come down?

Since 2020 the superstack has been inactive but work on preparing it for dismantling has not stopped. Careful study and design work was needed to ensure the dismantling was safe for the community and our employees working in the smelter complex. Time was spent slowly cleaning the stack's interior, removing the steel liner and sealing or removing accessory structures in preparation for a future dismantling of the shell.  

We are currently evaluating the approach to its dismantling, and we will keep the community informed as our plans develop. 

Photo: Andrew Edgerton

FAQs 

Since 2020, we have been preparing the superstack for dismantling. We have spent time slowly cleaning the stack’s interior, removing the steel liner, and sealing or removing accessory structures. We also took time to preform careful study and design work to ensure that when it is eventually dismantled that it is safe for the community and our employees working in the smelter complex.

Since the superstack's decommissioning in 2020, Vale has been approached by various groups with alternatives to dismantling. These ideas are unfeasible based on several factors: 

Safety and Access: The superstack is wholly contained within Vale’s Copper Cliff Smelter Complex property and there is no safe viable public access. As an active and busy industrial site, access is strictly controlled and monitored for safety as there are hazardous materials and moving equipment moving throughout the complex. Our policy requires visitors to wear personal protective equipment and be escorted when moving within the smelter.  

Practicality: Vale understands and appreciates the superstack’s significance to Sudbury's identity and history. However, maintaining such a large structure isn't just about preserving a landmark—it's about ensuring the safety, viability, and sustainability of that decision. The costs involved aren't merely financial; they include ongoing safety considerations, environmental impacts, and the infeasibility of adapting an aging industrial structure for modern use. For these reasons, a decision to apply resources to dismantle the superstack is the responsible way to serve current and future generations.

Neighbourhood impact: The superstack and the Copper Cliff Smelter Complex are located directly beside one of Greater Sudbury’s oldest and most historical residential neighbourhoods known as Little Italy. The roads in this neighbourhood are narrow, parking is limited, and land is unavailable. Any proposal that seeks to redevelop the superstack for non-industrial use would increase vehicle traffic and parking needs. This would directly impact the quality of life for residents living in this community. 

The concrete exterior will be cut in 4-foot sections. These pieces will be dropped down the middle of the chimney and collected for removal. Watch this animation to see how the process works.

Dust will be managed through stringent dust control methods, which include both active and passive strategies. Active methods include water misters, dust suppressants, and dust filtering. Passive methods will include enclosing the work area to capture the dust.  

Sound will mitigated by enclosing the work area at the platform level and by using blasting mats at the base of the stack for falling material. 

General concerns or questions about this work can be reported to Vale’s Community Concerns Line at (705) 222-8253. Calls are answered 24 hours a day, 7 days a week. Alternatively, individuals can email ontario.operations@vale.com

QM Environmental will dismantle the copperstack. They are one of Canada’s largest and most trusted demolition contractors. They have extensive experience with complex projects. 

ICC Commonwealth is responsible for the superstack dismantling. They specialize in large-scale and piecemeal chimney demolition and have expertise working around the world dismantling large concrete chimney stacks.  

It is expected that the combined cost to dismantle both chimneys will cost over $100 million dollars. 

The copperstack dismantling project is expected to last until the spring of 2025.  

The superstack dismantling project will take approximately 5 years to complete. The timeline of this project is longer due to the size of the chimney. 

The concrete shell will be removed from the Smelter area and placed in a designated area within Vale’s Central Tailings Facility. This location is designed for this purpose and will ensure that the rubble is safely contained, monitored and that all contact water is treated.  

If you have a question, want to leave a comment, or simply share a memory of the superstack (pictures are welcome), you can email superstack@vale.com

Farewell Superstack Commemoration Vote  

The skyline of Sudbury is about to change and that marks and end of an era for our city.  In recognition of the superstack’s association with the area’s identity, Vale is inviting the community to help us decide how to commemorate the superstack.

Each proposal listed below seeks to ensure that the superstack continues to resonate within the community it has long shaped.
 

Click the image to vote

Please choose one of the following ideas: 

1. A monument to the superstack to be located within the City of Greater Sudbury.

2. A  mural to be located within the City of Greater Sudbury. 

3. A digital commemorative archive with a charity coffee table book. 

Photo: Vale’s Archive

The voting period will close at 4:00 pm on Friday, September 27 and the winning proposal will be shared on our Facebook page in October 2024.

Share your memories!

Do you have memories or photos of the superstack? Share them with us at superstack@vale.com and Vale in Canada & UK Facebook