3/3/23

Environment, Iron Ore

Vale begins reusing tailings at Carajás dam using equipment with zero CO2 emissions

Gelado project starts commissioning with 100% electric dredges that will extract tailings deposited over the last 37 years

Vale has begun commissioning the Gelado Project in Carajás, in the state of Pará (Brazil), which will produce high-quality pellet feed by reusing the tailings that have been deposited in the Gelado dam since 1985, when Vale began operating in the region. In addition to providing a sustainable destination for the tailings, the project will use 100% electric dredges to extract the material, avoiding CO2 emissions. The initial production capacity will be 5 million tons per year and the investment is US$ 428 million. 

The commissioning phase, in which performance and capacity tests with loading are being carried out, should last until the end of the first half of the year, when operation will begin on a continuous basis. After the conversion of Carajás Plant 1 to natural humidity processing, planned for the next few years, the Gelado project will reach its capacity of 10 million tons per year. 
 

Electric dredge at Gelado project, in Carajás, Pará, Brazil. Credit: Felipe Borges/ Vale

Over the last 37 years Vale has been producing iron ore at Carajás and depositing the tailings in the Gelado dam. This material is basically composed of iron ore particles that could not be used in the original beneficiation process and impurities such as silica and alumina. Using dredges, the tailings will be removed from the dam and sent back for processing at the plant. 

The ore grade of the material extracted from the dam is already 63%, considered high. At the plant, the ore will undergo a magnetic concentration process, in which a powerful magnet separates the ferrous particles from the silica and alumina, further increasing its quality. This is the first time that magnetic concentration has been used in Pará's operations. 

The end product is a pellet feed that will feed the company's pelletizing plant in São Luís (in the state of Maranhão, Brazil). The high quality of the pellets manufactured at the site contributes to reducing carbon emissions for steelmaking customers when compared with lower quality products. Vale has a target of reducing its scope 3 emissions by 15% by 2035. 

The sustainable character of the project is reinforced by the use of 100% electric dredges, as well as electric pumps, which use electricity from renewable sources rather than fossil fuels such as diesel. Thus, over 10 years, the project will stop emitting a total of 484,000 tons of CO2, equivalent to the consumption for one year of 105,000 gasoline-powered 1,000-cc cars . The dredges, of Dutch technology, are 46 meters long and weigh 364 tons. 

"The environmental issue has been in focus since the conception of the Gelado project," explains the project's operations manager, Roberto Francisco. "In addition to desilting the dam, we are reducing the amount of tailings in the structure and transforming them into a new product, avoiding the necessity of future raisings. We do this by focusing on reducing CO2 emissions”. 

About 185 professionals will work directly on the operation. A total of ten inspectors and machine operators were professionally trained in the Netherlands to work with the dredgers. The investment enhanced the development of local professionals prepared to practice state-of-the-art and more sustainable mining. 

Circular economy and waste valorization

Vale researches and develops processes to reduce waste generation and to reuse or recycle these materials, giving rise to new products that contribute to a more sustainable value chain. In addition to reinserting rejects into the production chain, as is being done with Gelado, the company invests in reusing sand from iron ore processing in order to reduce the generation of tailings. 

In 2021 Vale started marketing Sustainable Sand, a product intended for civil construction with 100% legal origin, high silica and low iron content, and high chemical and grain size uniformity. So far, about 800,000 tons of the product have been donated or commercialized. The estimate for 2023 is that this quantity will grow. 

Vale is also developing solutions for using sandy tailings to pave roads and even as a substitute for common cement. 

Low carbon

The use of electric dredges at Gelado is part of Vale's initiatives to achieve its carbon emission targets. In 2020, Vale announced its goal of zero net emissions of Greenhouse Gases (GHG) by 2050, in scopes 1 and 2. Among the measures adopted to achieve this goal is the replacement of fossil fuels with clean sources in operations, focusing on the use of renewable energy and alternative fuels, greater efficiency in operations using new technologies. 

The strategy of electrification of assets, for example, already includes the adoption of two 72-ton electric trucks in mining operations in Indonesia and in the state of Minas Gerais (Brazil); and also about 50 pieces of underground mine equipment in Canada. 

 

Media Relations Office - Vale
imprensa@vale.com

Content with Press topics Iron Ore .

Lupa de pesquisa

Did not find what you were looking for? Access our Search Center 

Reparation

Our commitment to repairing the communities and people impacted by the B1 dam failure is constant. See the social, environmental and safety actions taken by Vale. 
Imagem placeholder Imagem placeholder Foto:
Onda