Zárás

menu-img-alt vale-wave
Imagem de header interno Imagem de header interno
2021. 07. 19.

Business

2Q21 Production and Sales Report


Vale completed another quarter of iron ore production growth (+11%q/q) and achieving a current capacity of 330 Mtpy, which if sustained could allow for an average of 1 Mt per day production in 2H21, due to the favorable seasonality from better weather conditions in the period. The unmanned train operation in Timbopeba is performing well and the maintenance of ship loader 6 (CN6) at the Ponta da Madeira Maritime Terminal was executed as scheduled, causing no impact in this year’s expected shipments. On Base Metals, the first ore production on its Reid Brook deposit at the Voisey’s Bay Mine Expansion Project was an important achievement to the continued delivery of quality, predictable and responsibly sourced material to market. 

Vale’s iron ore fines production totaled 75.7 Mt in 2Q21, 11.3% higher than in 1Q21, as a result of: (i) higher volumes from Brucutu with the increase of high-silica sinter feed production by dry processing taking advantage of a very favorable market environment; (ii) seasonal improvement of weather-related conditions in Serra Norte and a strong performance in Serra Leste; (iii) higher productivity in Itabira Complex, with the reassessment of temporary tailings management solutions; (iv) higher third-party purchase; and (v) wet processing production in Fábrica during the tests to resume beneficiation plant operations. Those positive results were partially offset by the interferences (tie-in effect) caused by the installation and commissioning of the first of four jaspilite crusher in S11D. 

Considering the iron ore mining plan and the implementation of new initiatives, Vale achieved a production capacity of 330 Mtpy, mainly as a result of Serra Leste achieving full capacity. The start-up date of some operations were revised due to the time required to receive their respective authorizations, namely (i) Vargem Grande conveyor belt resumption (now expected for 3Q21); (ii) to continue Fábrica’s wet processing production (now expected for 3Q21); and (iii) Torto dam in Brucutu following the need of extra works to increase safety factor (now expected for 2H22). 

Vale’s pellet production totaled 8.0 Mt in 2Q21, 27.4% higher than in 1Q21, although still limited by pellet feed capacity. Quarterly increase is mainly explained by the seasonally higher pellet feed availability which was mainly directed to Oman plants and by the ramp-up of Vargem Grande pellet plant. 

Sales volumes of iron ore fines and pellets totaled 74.9 Mt in 2Q21, up 14.2% higher than in 1Q21, as iron ore production increased. Iron ore price premium was US$ 8.4/t , in line with 1Q21, following higher pellet, IOCJ and BRBF premiums, which were offset by a higher share of high-silica products with the increase of sinter feed production by dry processing, taking advantage of a strong market environment. 

Production of finished nickel was 41.5 kt in 2Q21, 14.3% lower than 1Q21 mainly due to the labour disruption at Sudbury and unscheduled maintenance in Clydach Nickel Refinery, which impacted total production from material sourced from PTVI. 

On June 1st, 2021, production and maintenance employees represented by the United Steelworkers (USW) Local 6500 in Sudbury voted to reject the Company’s offer for a new five-year collective bargaining agreement, resulting in a labor disruption at Sudbury operations. Meanwhile, Vale implemented contingency plans to preserve the integrity and safety of the plants and mines. 

Copper production reached 73.5 kt in 2Q21, 3.9% lower than 1Q21 resulted from the labour disruption in Sudbury and delays in mining at Voisey’s Bay, partially offset by a more robust performance in Salobo due to the ramp-up of mine maintenance activities and better performance at Sossego operations. 

In line with COVID-19 safety measures, which limited the mobilization of contractors, Vale decided to only perform the critical maintenance activities in Sossego’s SAG mill in 2Q21. This has allowed the deferral of a major portion of the SAG mill maintenance to 2022. Vale expects production improvements as of 2H21. 

Also, movement at Salobo mine is improving with increased availability of equipment as the ramp-up of the mine maintenance workshop continues. Total mine movement at Salobo has increased 31.2% in Q2 compared to Q1, achieving 8.4 Mt in June. Improvement in mine movement is expected to continue in Q3. 

Given uncertainties concerning the labor situation in Ontario and the ramp-up of the safety and maintenance process implementation in Sossego and Salobo, our guidance for nickel and copper for the year is under review.

 

Media Relations Office - Vale
imprensa@vale.com

Lupa de pesquisa

Did not find what you were looking for? Access our Search Center 

Reparation

Our commitment to repairing the communities and people impacted by the B1 dam failure is constant. See the social, environmental and safety actions taken by Vale. 
Imagem placeholder Imagem placeholder Foto:
Onda